Results:
Tag: water management
Clear
  • USACE Kansas City District announces likely cancellation of fall water release from Rathbun Lake

    Unless conditions improve by the end of the first week of October, the fall water release previously announced by the Kansas City District, U.S. Army Corps of Engineers, will be cancelled. In July USACE announced tentative plans to perform the fall water release at Rathbun Lake. Currently conditions do not favor the water release as the pool elevation is near the multipurpose level of 904.0 feet.
  • USACE announces planned fall release from Rathbun Lake on Chariton watershed

    The public is invited to comment on the Rathbun Lake fall release as permitted in the revised 2016 Rathbun Lake Water Control Manual. The fall release will occur likely between the last week of September through early October 2022. The release of water will not exceed 2,700 cubic feet per second from Rathbun Reservoir and would be on-going for no longer than three or four days, excluding the ramp up and ramp down.
  • USACE Kansas City District holds exercise at Truman Lake to strengthen dam safety coordination with local authorities

    Local Emergency Management Agencies are the front lines of emergency preparedness in your community. They work in close coordination with U.S. Army Corps of Engineers and other agencies. USACE regularly assesses conditions and risks associated with our Civil Works projects, which include 18 dams with reservoirs. Eight are in Missouri, eight are in Kansas with one each in Iowa and Nebraska.
  • Stockton Lake releases increased

    Due to sustained high inflows into Stockton Lake since March 12th, releases of 5,500 cubic feet per second, or cfs, and up to 6,300 cfs will continue as downstream conditions allow.
  • Pomme de Terre Lake releases increased

    Pomme de Terre Lake continues to maintain high inflows that began on March 12th and is expected to continue through early spring. The lake will continue to maximize releases of 3,000 cubic feet per second, or cfs, up to 3,500 cfs as downstream conditions allow.
  • Tuttle Creek Lake prepares for winter: Outflow increases, lake drops

    MANHATTAN, Kan. – Beginning Dec. 23, 2020 the U.S. Army Corps of Engineers at Tuttle Creek Lake will increase outflows to drop lake levels in order to facilitate ongoing construction projects. This seasonal adjustment minimizes ice damage, provides additional storage capacity for spring rains and favorable habitat for fish spawning in the spring. Operations to lower the lake water level will not delay ongoing construction activities at the stilling basin (locally known as the “tubes”) nor cause excessive flow for ongoing construction downstream in the Kansas River.
  • Corps of Engineers at Tuttle Creek Lake prepares for winter - increasing outflow and dropping lake elevation

    Beginning November 25, Tuttle Creek Lake, Kansas City District, U.S. Army Corps of Engineers, will increase outflows to drop lake levels, consistent with the annual Water Level Management Plan.
  • Public invited to comment on planned autumn releases from Rathbun Lake

    In 2016 in response to stakeholder input, the Corps of Engineers revised its operating guidance for Rathbun Lake. The new guidance allows for an annual opportunity, every autumn, for the lake to schedule a release of water to benefit state and privately managed conservation and recreational areas downstream in the Chariton watershed. This release of water will not exceed 2,700 cubic feet per second from Rathbun Dam and would be sustained for no longer than 3 or 4 days, excluding ramp up and ramp down.
  • Corps approves temporary modifications to lake water management plans

    KANSAS CITY, Mo. — Due to ongoing challenging conditions with wet soils and higher than normal river levels across the Missouri River Basin, the U.S. Army Corps of Engineers, Kansas City District is canceling plans to increase water levels in reservoirs for the spring as stated in the annual water level management plans.    This temporary modification will better position the Kansas City District's reservoirs to receive spring runoff, and manage for locally heavy rainfall following record lake levels across the district last year. Nine of 18 district reservoirs reached record pools in 2019. Flood control operations at Kansas City District Reservoirs and Bureau of Reclamation lakes prevented $131 million in damages in Kansas and $2.27 billion in damages in Missouri during the 2019 flood event. Life safety and flood control are primary factors in reservoir operations throughout the Missouri River Basin.
  • Corps at Rathbun Lake to conduct a fall pulse in late September

    In 2016, the U.S. Army Corps of Engineers updated the Chariton River Water Regulation Manual and incorporated new adaptive water management strategies benefiting interests both upstream and downstream of the Rathbun Lake dam. One of the adaptive water management strategies in the new manual allows for a ‘fall pulse’ or increased water release for a short duration from the lake. This fall pulse gives the Corps the ability to increase water in support of downstream wildlife management goals on state and privately owned lands.