2019 Levee Rehab Status Report



Updated: 25 March 2020
The Kansas City District Corps of Engineers expects a two year duration for levee rehabilitation
and does not expect to have levees repaired prior to spring 2020.
13 Contracts Awarded: Henry Pohl, Grape Bollin Schwartz, KS Dept. of Corr., Mi‐De, East Bottoms, Labadie 4/5/6, Berger, NKC 2018, R‐471‐460, Cambridge, NE Saline, Jacobs/Tebbets, Wainwright
13 Contracts with open bids and Award processing: Whitam/GardenEden 1, GardenEden 2/3, Howard 4, Capital View, Cole Junction, Mokane, Steedman, Hartsburg 1/2/3, A‐1 (RFP), Morrison (RFP), Cooper County, Howard 2, Wolcott1/2/3
6 Contracts Currently Advertised with Bid Opening Date: Platte County2/Bean Lake (26‐Mar), Ray Lafayette/HCR1 (7‐Apr), Renz (19‐Apr), L‐400/L‐408 (7‐Apr), R‐440 (9‐Apr), Sugartree (Proposal due Mar 25)
4 Contracts pending Advertisement and USACE Action: Morrison (revising RFP), Tricounty/Egypt, Bonne Femme, Malta/Coles/Saline/Teteseau
12 Contracts need Sponsor PCA, Real Estate Certification, Tax ID Number, or Cost Share: Tuque Creek, R500, Lower Chariton, L246, Kimsey Holley/L‐497/L‐488/L‐455/L‐448‐443, Brunswick, Canon, Dewitt 1/2, Saline County 2, Wakenda, Miami, Plowboy
4 Contracts with Borrow Area or Site Features being coordinated with Sponsor: Holt 9, Platte County2/Rushville, Reveaux, MO Valley Sec ½
15 Contracts in Project Information Report/Damage Assessment Phase: Corning, MO Valley D&LD, Ray Carroll, Union Townshiop/Holt 10, N Topeka, S Topeka, Abilene‐LB, Abilene‐RB, R‐351‐1, R‐351‐2, CIDMO, Argentine, Armourdale, Soldier Crk, Salina
***Withdrawn (West Glasgow, McBaine, Big Bend, Linneman‐Weekley) and Ineligible (Chamois, 476, and 482) requests have been removed