Background: Levee District No. 7 Howard Co., Section 4 is a non-federal levee in Howard County, Missouri, and experienced significant damage during the 2019 Flood Event.
Current Action: Please check back for more details.
Emergency Flood Fighting Operations:
|
Direct Assistance Repair |
Contractor
|
R&L Boone
|
Contract Amount
|
$216,150
|
Contract Award
|
4/1/2020
|
Construction Start
|
4/13/2020
|
Estimated Completion
|
October 2020
|
Next Steps: Levee repairs on the Missouri River will not be completed prior to the 2020 Spring Flood Season. Some communities along the river will have an elevated flood risk.