Background: Howard Co. No. 2 is a non-federal levee in Howard County, Missouri, and experienced significant damage during the 2019 Flood Event. (Breach, Overtopping, Levee Slope Slides, Scour, Grass Kill)
Current Action: Contract award
|
Direct Assistance Repair |
Contractor
|
R&L Boone
|
Contract Amount
|
$216,150
|
Contract Award
|
4/1/2020
|
Construction Start
|
TBD
|
Estimated Completion
|
TBD
|
Next Steps:
The Kansas City District continues to prioritize levee rehabilitation to repair damages incurred during 2019 historic flooding throughout the region. We are also committed to providing on-site quality assurance to awarded construction contracts all while practicing social distancing as long as necessary.
Challenging weather conditions may result in project delays.