Background: 408-L is a federal levee and experienced significant damage during the 2019 Flood Event.
Current Action: Contract awarded
|
Direct Assistance Repair |
Contractor
|
HB Construction
|
Contract Amount
|
$337,024
|
Contract Award
|
5/7/2020
|
Construction Start
|
5/18/2020
|
Estimated Completion
|
Fall 2020 |
Next Steps: Levee repairs on the Missouri River will not be completed prior to the 2020 Spring Flood Season. Some communities along the river will have an elevated flood risk.